Al Taif – Al Baha Water Transmission System, KSA
CLIENT NAME Arabian Pipeline Projects Company (APPCO)
OWNER Saline Water Conversion Corporation
LOCATION KSA
DURATION 2011 – Ongoing
PROJECT ESTIMATED VALUE SAR 1.2 Billion
Overview:
  • Detailed engineering services for Al Taif – Al Baha water transmission system in Saudi Arabia
  • The Water Transmission System consists of:
    • Al Taif Pump Station ARADA (2 sets of pumps, flow rates 636 l/sec. and heads 370,160 m)
    • Reservoirs of (Al Baha, Shuhada, Sudyrah, Shugsan, Gazail, & Mandaq) with capacities from 1500 to 140,000m3
    • Transmission main pipe line of diameter 1000 mm from steel pipes with total length about 200 km
 
Scope:
  • Providing detailed design for the main pipe line including preparing pipe alignment sheets, stress analysis, determine the wall thickness for the steel pipes and its grade
  • Preparing the detail design for all the civil, electrical, mechanical, landscape and architectural works for the main pump station (PS ARADA) and all the reservoir stations along the pipe line route