EPC of Primary Electrical Substation # 3 (380/115/33kV) in Ras El Khair, KSA (Contract No. 099-C05)
CLIENT NAME Royal Commission for Jubail and Yanbu, KSA
OWNER Royal Commission for Jubail and Yanbu, KSA
LOCATION Ras El Khair, Jubail, KSA
DURATION 2013 - 2017
PROJECT ESTIMATED VALUE SAR 500 Million
Overview:

This project is a part of RC contract no. (027-T09) for Power and Telecommunications Engineering Services and located in Ras El Kheir project includes two parts:

  • Indoor type GIS 380/115/33kV electrical substation#3 
  • 380kV overhead transmission line to connect SS#3 with three (3) existing substations

 

Objectives

  • The substation shall equipped with Substation Automation System (SAS)
  • The substation shall be remotely controlled through SCADA system
  • The project also includes the necessary modifications/additions to the protection, control, communication, SCADA and associated equipment at remote end 380kV substations supplying power to substation#3
 
Scope:
  • Preparation of project technical specifications/ Scope of Work (PTS/SOW)
  • Preparation of Request for Proposal (RFP)
  • Drawings