Abu Rawash WWTP Extensions, Giza, Egypt
Client
The Arab Contractors (AC)
Owner
The Construction Authority for Potable Water and Wastewater (CAPW)
Project Estimated Value
EGP 2 Billion
Location
Abu Rawash, Western Sector of Giza, Egypt
Duration
2005 – 2008
Project Description
The WWTP is working by Primary Treatment with an average capacity of 400,000 m³/day. The Arab Contractors has made the necessary expansions for the plant to reach a capacity of 1,200,000 m³/day. The project includes Transmission of Treated WW from Abu Rawash WWTP to Green Buffer of 6ᵗʰ October City.
Scope
Preparing detailed design drawings for both main treatment and extensions as follows:
- Power House Building No. (45)
- Generator Building No. (50)
- New substation Building No. (51)
- New medium voltages switch board building No. (52)
- Effluent channel to Barakat Drain
- Collecting Channels of 8 Primary Settling Tanks (PST)