Souq Waqif Substation, Qatar
(11/0.415kV)
Client
Private Engineering Office (PEO)
Owner
Private Engineering Office (PEO)
Project Estimated Value
QAR 25 Million
Location
Souq Waqif Area, Qatar
Duration
2013 – 2014
Project Description
The project consists of 3 stages as follows:
- Stage-1: Data gathering and studying the existing network
Study of the Existing MV and LV network
Identify the areas/buildings being served by the existing LV Panels/Substations
Identify the no. of the outgoing cables from the existing LV Panels
Relocation of the existing substations (S/S nos. 4093 and 0418) and combine these 2 substations into 1 underground substation
- Stage-2: Design work
Substation Building, Infrastructure work, and Approvals
- Stage-3: Tender Stage
Scope
Design, tendering and construction supervision