CANRCC Upgrade Project, Ismailia, Egypt
(Consulting services and Technical Assistance)
Client
Fichtner GmbH
Owner
Egyptian Electricity Transmission Company EETC
Project Estimated Value
USD 19 Million
Location
Canal Regional Control Center in Ismailia, Egypt
Duration
2018 – 2021
Project Description
Canal Regional Control Center (CANRCC) Upgrade Project is to achieve the proper and effective monitoring, managing and controlling of all the 66 /22-11 kV substations and its 66kV transmission network as well as monitoring of 500 & 220kV transmission network in Canal zone area. The project implements full scale modern communication and SCADA systems to monitor, manage and control in a safe and reliable manner the relevant network as well as monitoring energy exchanges in the zone interconnections with other zones under the authorization of the National Energy Control Center (NECC).
Scope
Construction supervision for the following disciplines:
- SCADA/EMS system of the EETC Canal RCC (CANRCC) Ismailia,
- RCC Facilities (BMS, UPS, Diesel Generator, HVAC, Firefighting & Fire detection, CCTV),
- RTU/Adaptation works, DC system at approximately 110 outstations of the EETC Canal sites,
- Telecommunication works & associated equipment at CANRCC Upgrade project,
- OHL Line OPGW Works,
- Accountancy works