Improved W&WW Services Programme (IWSP 1)
Project #4, Gharbia, Egypt
Client
Gharbia Water and Wastewater Company
Owner
Gharbia Water and Wastewater Company
Project Estimated Value
EGP 350 Million
Location
Gharbia, Egypt
Duration
2017 – 2019
Project Description
The project is part of the IWSP program (Phase 1), and includes the construction supervision of sewage network for Al Mahala Al Kubra 1+2, Gharbia Governorate including the following:
- Al Mahala Al Kubra 1 (Shubra Malkan & Ayash about 23,000 inhabitants
- Al Mahala Al Kubra 2 (Ezbeth & Om El Seteen about 1400 inhabitants
The project comprises; gravity sewers with house connection, pumping mains, sewer pumping stations and channel crossings
Scope
- Design review and evaluation of tender documents
- Construction supervision works for the sewage networks & pumping stations
- Testing and commissioning according to FIDIC contracts provisions
- Assistance to the PIU department during the Defects Notification Period
- Final taking over of the project