1ˢᵗ Stage of Shorook City WWTP & Adding Tertiary Treatment for the Hykstep WWTP, Egypt
Client
The Construction Authority for Potable Water and Wastewater (CAPW)
Owner
The Construction Authority for Potable Water and Wastewater (CAPW)
Project Estimated Value
EGP 330 Million
Location
Shorook City, Egypt
Duration
2009 – 2018
Project Description
1st Shorook City WWTP: Collect the raw wastewater, treat it a tertiary treatment, reuse in the irrigation of the city landscape & design to reach a capacity 200,000 m³/day
2nd Hykstep WWTP: Tertiary treatment now is being added to the plant with capacity 27,000 m³/day.
3rd Main Irrigation network for Shorook City: Pipeline diameters (100 – 900 mm), with total length 300 km. Provide survey data for pipeline in coordination with the contractor
Scope
Detailed design drawings review, technical specification and construction supervision