1ˢᵗ Stage of Shorook City WWTP & Adding Tertiary Treatment for the Hykstep WWTP, Egypt

Client

The Construction Authority for Potable Water and Wastewater (CAPW)

Owner

The Construction Authority for Potable Water and Wastewater (CAPW)

Project Estimated Value

EGP 330 Million

Location

Shorook City, Egypt

Duration

2009 – 2018

Project Description

1st Shorook City WWTP: Collect the raw wastewater, treat it a tertiary treatment, reuse in the irrigation of the city landscape & design to reach a capacity 200,000 m³/day

2nd Hykstep WWTP: Tertiary treatment now is being added to the plant with capacity 27,000 m³/day.

3rd Main Irrigation network for Shorook City: Pipeline diameters (100 – 900 mm), with total length 300 km. Provide survey data for pipeline in coordination with the contractor

Scope

Detailed design drawings review, technical specification and construction supervision